(703) 403-4656
NEW PROJECT | Completed in 7 Days

AMSS completes yet another challenging CLS project. Completed on site in just seven (7) days with generator power running lights and HVAC units at the end of the first day. Day Two was spent welding all foundation and CLS mateline and roof connections. Days Three and Four included roof completion and interior carpentry connections. Days Five and Six included interior electrical connections, grid power/utility meter installation and fire system commissioning, and Day Seven included final punch list items and site clean up. Immediately after the CLS buildings were complete the the ground loop and DC Power Plant were installed!