(703) 403-4656
AMSS Finishes Its Second North America CLS Project for 2016 | Completed in just 7 Days

AMSS completed yet another challenging CLS project in North America. Completed on site in just seven (7) days with generator power running lights and HVAC units at the end of the first day. Day Two was spent welding all foundation and CLS mateline and roof connections. Days Three and Four included roof completion and interior carpentry connections. Days Five and Six included interior electrical connections, grid power/utility meter installation and fire system commissioning, and Day Seven included final punch list items and site clean up. Immediately after the CLS buildings were complete the DC Power Plant was installed!